Summary
The developer testified it's seeking $3-5 million in design and permitting help for a temporary package wastewater plant in case the Central Maui facility isn't online by 2029-2030 — an insurance policy to keep roughly 600 housing units moving.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 24, 2026.
Impact analysis
Roughly $3-5 million sought for design and permitting; plant construction estimated at $5-6 million.
Waikapu Country Town homebuyers and the wider Central Maui housing pipeline, including the future school site.