North-South Collector Road and eminent domain

Maui County

Summary

Mayer called Piʻilani an eight-to-ten-mile cul-de-sac and estimated 6,800 additional vehicles if all planned units build out; the possible road link to Veterans Highway is a two-lane road with no funding in the plan.

At a glance

Total mentions
5
Last 30 days
1

Rising — discussed at 4 meetings since Sep 14, 2026, up from 0 in the two months before.

Impact analysis

💰Financial impact

First phase estimated at $72-75 million and expected to rise; current funding is only about half of what's needed to reach Kaonoulu.

✅Who benefits

Commuters if the collector road and bypass actions move forward with easements secured early.

⚠️Who could be affected

Kīhei drivers face potential 'paralysis' on Piʻilani if growth arrives before relief roads.

Mentions & discussions (5)

MeetingOct 5, 2026

Disaster Recovery, International Affairs, and Planning Committee (2025-2027) — October 5, 2026

The plan's North Kihei Mauka policies tie development to a two-lane collector road connecting East Lipoa Street to Veterans Highway, and require homes be owner-occupied or long-term rentals for local residents. Members floated asking the MPO for a route study and including the state veterans home and DHHL lands in the road conversation.

MeetingSep 24, 2026approved

Disaster Recovery, International Affairs, and Planning Committee (2025-2027) — September 24, 2026

Director Molina asked the committee to split the collector road action into phases — the current $81 million Waipuilani-to-Kaonoulu segment, and later segments toward Alahaoe Road — since costs and timelines differ per phase.

MeetingSep 21, 2026

Disaster Recovery, International Affairs, and Planning Committee (2025-2027) — September 21, 2026

Mayer called Piʻilani an eight-to-ten-mile cul-de-sac and estimated 6,800 additional vehicles if all planned units build out; the possible road link to Veterans Highway is a two-lane road with no funding in the plan.

MeetingSep 14, 2026

Disaster Recovery, International Affairs, and Planning Committee (2025-2027) — September 14, 2026

The plan's top transportation priority: extending Liloa Drive as a two-lane road with linear park and paths. First phase runs $72-75 million, design is 60% complete, and construction could start early 2028 under a federal RAISE grant.

MeetingApr 10, 2026

Budget, Finance, and Economic Development Committee (2025-2027) — April 10, 2026

The roughly $27 million RAISE-grant-funded road needs right-of-way by September 2027; some holdout property owners may force the county to pursue eminent domain. Council Member Cook supports moving fast.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Maui County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.